News

Sanctuary A/C Update: 4/19/24

After standing down construction during Holy Week, the crew is back on site, and we are in the home stretch.

  • All work in the sanctuary is complete with the installation of the registers. Side aisles and ambulatories are fully open.
  • Power wiring to the air handlers is complete and control wiring is in process.
  • The new door to the atrium is installed.
  • Painting has started
  • Ceiling and lighting installation will start in the next few days
  • Ductwork is 100% complete.
  • The construction barrier at the top of the sacristy stairs is still in place and will be for a little while longer.

We are on track for an end-of-April completion.  Stay cool.

Here are few photos of the work in progress.

South Aisle Registers

North Aisle Registers

Condensing Units

Condensate Piping Installation